Table Of contents
About the author
Disclaimer
EXECUTIVE SUMMARY
Opportunity sizing
Rollout economics
Levers of a successful rollout
Opportunity sizing
Summary
Introduction
Size of addressable customer base
Mandatory targets
Current installed base
Installed base forecast
Achievable penetration rates
Technology choice
Ramp-up timings
Market value
Rollout cost structure
Unit cost estimates
Vendor opportunity
Rollout economics
Summary
Introduction
Customer benefits
Sources of customer benefit
Illustrative customer scenarios
Supplier benefits
Sources of supplier benefit
Illustrative supplier scenarios
Benefit sharing
Tariff innovations for electricity customers
Tariff rises for gas customers
Investment scenarios
Base case scenarios
Price sensitivities
Levers of a successful rollout
Summary
Introduction
Critical success factors
Taxonomy of critical success factors
Outcome sensitivities of critical success factors
Recommendations
Recommendations for suppliers
Recommendations for other market participants
List Of Tables
Table: Electricity customer type definitions (conceptual), 2012
Table: Switchover targets by customer type (conceptual), 2012–19f
Table: Number of SME electricity and gas sites in the UK (million units), 2012e
Table: Number of smart/advanced meter installations (million units), 2020f
Table: Deployment phasing strategies (percentage of total per annum), 2012–19f
Table: Cumulative smart/advanced meter installations (million units), 2012–20f
Table: Estimated unit costs of on-site equipment (£), 2012–20f
Table: Projected installation costs per site (£), 2012–20f
Table: Annual supplier capex (£m), 2012–20f
Table: Customer benefit scenario, SME 3–4 electricity user (£ per annum), 2014f–20f
Table: Customer benefit scenario, SME 3–4 gas user (£ per annum), 2014f–20f
Table: Supplier benefit scenario, SME 3–4 electricity user (£ per annum), 2014f–20f
Table: Supplier benefit scenario, SME 3–4 gas user (£ per annum), 2014f–20f
Table: Scenarios of benefit allocation, typical electricity site (£ per annum), 2014f–20f
Table: Scenarios of benefit allocation, typical gas site (£ per annum), 2014f–20f
Table: Base case investment scenarios (£ per site), 2014f–20f
Table: NPV and break-even of converting a typical electricity site (£), 2014f–20f
Table: NPV and break-even of converting a typical gas site (£), 2014f–20f
Table: NPV of total benefit per site vs supplier's market share (£), 2014f–20f
Table: NPV of total benefit per site vs to take-up rate (£), 2014f–20f
Table: NPV of total benefit per site vs first-time installation rate (£), 2014f–20f
Table: NPV of total benefit per site vs reduction in consumption (£), 2014f–20f
Table: NPV of total benefit per site vs peak/off-peak substitution (£), 2014f–20f
Table: NPV of total benefit per site vs WACC (£), 2014f–20f
List Of Figures
Figure: Number of SME electricity and gas sites in the UK (million units), 2012e
Figure: Number of smart/advanced meter installations (million units), 2020f
Figure: Deployment phasing strategies (percentage of total per annum), 2012–19f
Figure: Cumulative smart/advanced meter installations (million units), 2012–20f
Figure: Smart metering cost structure (conceptual), 2012–20f
Figure: Non-residential on-premises hardware configuration (schematic), 2012–20f
Figure: Estimated unit costs of on-site equipment (£), 2012–20f
Figure: Projected installation costs per site (£), 2012–20f
Figure: Annual supplier capex (£m), 2012–20f
Figure: Customer benefit scenario, SME 3–4 electricity user (£ per annum), 2014–20f
Figure: Customer benefit scenario, SME 3–4 gas user (£ per annum), 2014–20f
Figure: Supplier benefit scenario, SME 3–4 electricity user (£ per annum), 2014–20f
Figure: Supplier benefit scenario, SME 3–4 gas user (£ per annum), 2014–20f
Figure: Scenarios of benefit allocation, typical electricity site (£ per annum), 2014–20f
Figure: Scenarios of benefit allocation, typical gas site (£ per annum), 2014f–20f
Figure: Base case investment scenarios (£ per site), 2014f–0f
Figure: NPV and break-even of converting a typical electricity site (£), 2014f–20f
Figure: NPV and break-even of converting a typical gas site (£), 2014f–20f
Figure: NPV of total benefit per site vs supplier's market share (£), 2014f–20f
Figure: NPV of total benefit per site vs take-up rate (£), 2014f–20f
Figure: NPV of total benefit per site vs first-time installation rate (£), 2014f–20f
Figure: NPV of total benefit per site vs reduction in consumption (£), 2014f–20f
Figure: NPV of total benefit per site vs peak/off-peak substitution (£), 2014f–20f
Figure: NPV of total benefit per site vs WACC (£), 2014f–20f